Camelback Residences Nearing a 2025 Completion with Uncompromising Craftsmanship

Construction continues to advance steadily at Camelback Residences as we move closer to completion. With significant progress both inside and out, the team remains focused on delivering luxury living with meticulous attention to detail. Below is the latest update along with a progress video.

EXTERIOR PROGRESS
Roofing is nearly complete, with work around elevator areas still in progress. Final handrails are being installed, and ground-level waterproofing is 99% complete. HVAC condensing units are in place and being prepared for startup. SRP transformer pads are set, secondaries pulled, and we’re awaiting SRP to install transformers and pull primaries. Patio cable installation is underway. Final grading and garage concrete entrance work are both scheduled to begin in the next two weeks.

INTERIOR PROGRESS
First Floor: The QC (Quality Control) process has started. Shower glass and fireplace tile installations are in progress. Corridors have been inspected and are ready for box walks and entry door front installations are in progress. In the loft units, box walks have started with drywall installation scheduled for next week.

Second Floor: Kitchen countertops have been installed, and other millwork is underway. Shower tile work is ongoing, and the corridor rough-ins are complete and ready for box walks.

Third Floor: Wood flooring, kitchen installation, painting, and tile work are all actively progressing. Baseboards and trim are being installed, and patio tile installation is underway.

Fourth Floor: The last three to four units are ready for drywall. Kitchen and wood flooring installations continue. Box walks are being scheduled for the remaining units, with electrical rough-ins nearing completion.

**BOX WALKS are conducted to ensure that electrical, plumbing, and structural components are being executed according to the plan.

Stay tuned for continued updates as we move toward anticipated closings in Fall 2025.